The pace of work has increased and this photo taken from inside the front gate structure shows the equipment and state of things at the beginning of the week.
The garden transformers have all been set and CFE has approved our underground vault and conduit installations and have allowed the electricians to complete the installation of the high tension underground lines. Telephone (Telmex) is next and should begin this next week.
The big CAT grader returned to the site to begin laying the thick gravel and sand base for Privada El Campanario, the upper road.
This view is taken by standing on lots 14 & 15 looking to where the cul-de-sac ends on Privada El Campanario.
The incredible mountain and lagoon views as seen from homes 5, 6, 7, 11 and 13.
A worker inspects his progress on the finish coat of cement stucco of the moldings on the front of the entry. Again, note the size of the man compared to the size of the structure. It's difficult to get a sense for the true size when people aren't in the photographs.
Looking up the hill from just inside the entry gates, the bell tower can be seen rising from the top of the hill. It's wintertime, and many of the trees are dormant right now. Later many coconut palms and native hardwood trees will be added along the road boundaries.
The finished and compacted road base awaits installation of pavers on Privada El Campanario, the road that leads to the eight top homes in Buena Vista.
The first arches begin to appear in the bell tower. The center platform level will be open to residents and their guests and is an excellent place to get 360-degree panoramic views of the area.
The pavers are being installed on the top of Privada El Campanario. This view shows a worker in the area of the boundary between lots 9 & 10.
An important part of creating new roads is dealing with rain water run-off to prevent erosion. This picture shows the partially completed rain gutter along the lower road.
A view of the rainwater drain from the road surface.
Because the stone blends into its native surroundings it's difficult to see, but the 2.3 meter high rock wall surrounding the water reclamation system is almost completed.
The stack of brick will be used to complete the front wall at the entrance on the left side. This wall will have a temporary construction entrance built into it for vehicles to use during home construction.
A worker stands on the footing for the wall. To his left is a temporary electric meter enclosure that will be removed once Buena Vista is connected to the main grid. The area along the road will be heavily landscaped.
Truckloads of sand are being delivered and brushed into Buena Vista's roads to fill the spaces between the paver blocks. The finished road surfaces look beautiful.
Jesus', our head contractor puts the finishing touches on the square column bases on the outside of the Buena Vista entrance.
The two new Tuscan columns have been roughed in on the front of the entrance to the office at the gate structure. This next week a decorative iron balcony railing will be added to the platform above the columns. Provisions were made during construction to allow for the addition of a bedroom and bathroom above the office level in the future.
The road base has been placed, graded, wet and rolled and made ready for pavers on Privada El Campanario, the road leading to the top of Buena Vista.
Curbstones are starting to be placed at the area around the entrance fountain and for the three parking spaces adjacent to the office and area where the future Spa will be located. By the end of next week we expect the paver installation of this area to be completed as well.
04-14-07 - A worker smoothes out a few rough spots in the moldings on the front of the entrance.
04-14-07 - Home buyers, Victor and Wilma Didkowski of Calgary arrive to take a look at the progress.
04-14-07 - Road pavers around the big Cantera fountain are almost complete. There are only the tiny cuts to be installed, and then they will be sanded.
04-14-07 - The area on the left will be heavily landscaped with large trees at the property line and toward the fountain, ornamental trees, bananas and other tropicals will be installed.
04-14-07 - The two columns in the distance will support a wooden pergola trellis above the entrance to the pedestrian gate and maintenance room. After construction is completed Bougainvilleas will be planted to cover the pergola.
04-14-07 - Workers finish up concrete work and get ready to start putting the waterproof coatings on the roofs of the entry structure.
04-14-07 - Another view of the front entrance area. This photo was taken from the lower edge of lot 16.
04-14-07 - The pavers on Privada El Campanario that leads to the upper eight lots in Buena Vista and the bell tower have been completed.
04-14-07 - Working sand in between the pavers is a Saturday family affair. This little toddler has having a great time helping her mom and dad.
04-14-07 - Lou, Victor and Wilma look at the views from the top. The transformation on the bell tower was dramatic this past week.. It no longer looks like a big elevator shaft ;-)
04-14-07 - Still wearing its scratch-coat of cement plaster, you can start to see the detail of the moldings emerge on the bell tower.
04-14-07 - A view through the side openings on the bell tower. A mason works high on the scaffolding to put the scratch coat on the sides of the tower where the bells will be located
Thumbnail panels:
|